Ball mill upgrade at Collahuasi increases processing capacity by 4.4%. The upgrade was achieved without safety incidents in 71 days, 13 days ahead of the initial schedule. It involved changing the rotor, GMD system stator and redesigning the mill discharge to achieve an increase in both available power and the level of filling required to treat ...